Cuong Quoc Vo, Hien Van Nguyen, Tra Thu Thi Nguyen, Thi Ngoc Huynh, Binh Thanh Le
Keywords
Tunnelling, surface settlement, volume loss, case study
Abstract
The 781m twin tunnel in line No 1 Ben Thanh – Suoi Tien was the first tunnels constructed by Earth Pressure Balance Tunnel Boring Machine (EPB TBM) in the urban area in Ho Chi Minh City, Vietnam. Field data on a surface settlement at three sections, measured during the construction period from May 2017 to June 2018, are used for back analyses on the development of surface settlement with the corresponding advancement of the EPB TBM. From there, the contributions of the main components of volume loss are determined which can be a useful reference for similar tunneling projects in the local area.
Downloads
Download data is not yet available.
23
Abstract Views
23
PDF Downloads